1.    An application for a route permit for an electric transmission facility within a designated corridor must be filed no later than two years after the issuance of the certificate and must be in such form as the commission may prescribe, containing the following information:

Terms Used In North Dakota Code 49-22-08.1

  • Amendment: A proposal to alter the text of a pending bill or other measure by striking out some of it, by inserting new language, or both. Before an amendment becomes part of the measure, thelegislature must agree to it.
  • Evidence: Information presented in testimony or in documents that is used to persuade the fact finder (judge or jury) to decide the case for one side or the other.
  • following: when used by way of reference to a chapter or other part of a statute means the next preceding or next following chapter or other part. See North Dakota Code 1-01-49
  • Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
  • Person: means an individual, organization, government, political subdivision, or government agency or instrumentality. See North Dakota Code 1-01-49

a.    A description of the type, size, and design of the proposed facility. b.    A description of the location of the proposed facility.

c.    An evaluation of the proposed route with regard to the applicable considerations set out in section 49-22-09 and the criteria established pursuant to section 49-22-05.1.

d.    A description of mitigative measures that will be taken to minimize all foreseen adverse impacts resulting from the location, construction, and operation of the proposed facility.

e.    A description of the right-of-way preparation and construction and reclamation procedures.

f.    A statement setting forth the manner in which:

(1) The utility will inform affected landowners of easement acquisition, and necessary easement conditions and restrictions.

(2) The utility will compensate landowners for easements, without reference to the actual consideration to be paid.

g.    Such other information as the utility may consider relevant or the commission may require.

2.    After determining that the application is complete, the commission shall serve a notice of filing of the application on such persons and agencies that the commission may deem appropriate and shall publish a notice of filing of the application in the official newspaper of each county in which any portion of the designated corridor is located.

3.    A copy of the application shall be furnished to any person or agency, upon request to the commission within thirty days of either service or publication of the notice of filing.

4.    An application for an amendment of a permit shall be in such form and contain such information as the commission shall prescribe.

5.    The commission shall designate a route for the construction of an electric transmission facility following the study and hearings provided for in this chapter. This designation shall be made in accordance with the evidence presented at the hearings, an evaluation of the information provided in the application, the criteria established pursuant to section 49-22-05.1, and the considerations set out in section 49-22-09 in a finding with reasons for the designation, and shall be made in a timely manner no later than six months after the filing of a completed application. The time for designation of a route may be extended by the commission for just cause. The failure of the commission to act within the time limit provided in this section shall not operate to divest the commission of jurisdiction in any permit proceeding. Upon designation of a route the commission shall issue a permit to the applicant with such terms, conditions, or modifications deemed necessary.