By January 1, 2024, the commission shall update General Order 131-D to authorize each public utility electrical corporation to use the permit-to-construct process or claim an exemption under Section III(B) of that general order to seek approval to construct an extension, expansion, upgrade, or other modification to its existing electrical transmission facilities, including electric transmission lines and substations within existing transmission easements, rights of way, or franchise agreements, irrespective of whether the electrical transmission facility is above a 200-kilovolt voltage level.

(Added by Stats. 2022, Ch. 357, Sec. 1. (SB 529) Effective January 1, 2023.)

Terms Used In California Public Utilities Code 564

  • Commission: means the Public Utilities Commission created by §. See California Public Utilities Code 20
  • Corporation: A legal entity owned by the holders of shares of stock that have been issued, and that can own, receive, and transfer property, and carry on business in its own name.