Indiana Code 36-9-39-29. Contractors; submission of monthly estimates of work done; issuance of certificates in payment; negotiability; interest; retainage
Indiana Code 36-9-39-1.3Terms Used In Indiana Code 36-9-39-29
(c) Certificates issued under this section (or under IC 36-9-21 before its repeal in 1993) are negotiable instruments.
(d) Interest on the certificates is payable out of the contract price and the special fund collected from the special assessments against the benefited property.
(e) If the municipality in issuing a contract for construction has required and obtained performance and payment bonds covering one hundred percent (100%) of the cost of construction, retainage shall be withheld as follows:
(1) This subdivision applies until the public work is fifty percent (50%) complete. The works board shall, on approval of contractor monthly payment estimates, issue to the contractor certificates for ninety percent (90%) of the amount shown to be due to the contractor.
(2) This subdivision applies after the public work is fifty percent (50%) complete. If the works board determines that the contractor is being responsive and responsible in carrying out the construction, the works board may, on approval of contractor monthly payment estimates, issue to the contractor certificates for one hundred percent (100%) of the amount shown to be due to the contractor.
As added by P.L.98-1993, SEC.10. Amended by P.L.1-1994, SEC.183.