24 CFR 891.165 – Duration of capital advance
Current as of: 2024 | Check for updates
|
Other versions
(a) The duration of the fund reservation for a capital advance with construction advances is 24 months from the date of issuance of the award letter to the date of initial closing. This duration can be up to 36 months, as approved by HUD on a case-by-case basis.
(b) The duration of the fund reservation for projects that elect not to receive any capital advance before construction completion is 24 months from the date of issuance of the award letter to the start of construction. This duration can be up to 36 months, as approved by HUD on a case-by-case basis.