(a) In this section:
(1) “Plan” means the 10-year dam repair, rehabilitation, and maintenance plan adopted under this section.
(2) “Water development board” means the Texas Water Development Board.
(b) The state board shall prepare and adopt a plan describing the repair and maintenance needs of flood control dams described by Subsection (c) and prepare and adopt a new plan before the end of the 10th year following the adoption of a plan.

Terms Used In Texas Agriculture Code 201.0227

  • Appropriation: The provision of funds, through an annual appropriations act or a permanent law, for federal agencies to make payments out of the Treasury for specified purposes. The formal federal spending process consists of two sequential steps: authorization
  • Department: means the Department of Agriculture. See Texas Agriculture Code 1.003
  • Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
  • Year: means 12 consecutive months. See Texas Government Code 311.005

(c) The plan must include projects under the jurisdiction of the state board and authorized under:
(1) Section 13, Flood Control Act of 1944 (Pub. L. No. 78-534);
(2) the pilot watershed program authorized under the Department of Agriculture Appropriation Act, 1954 (Pub. L. No. 83-156);
(3) the Watershed Protection and Flood Prevention Act (Pub. L. No. 83-566); and
(4) Subtitle H, Title XV, Agriculture and Food Act of 1981 (Pub. L. No. 97-98).
(d) The state board shall deliver the plan adopted under this section to the water development board.
(d-1) Repealed by Acts 2021, 87th Leg., R.S., Ch. 36 (S.B. 669), Sec. 2, and Acts 2021, 87th Leg., R.S., Ch. 856 (S.B. 800), Sec. 25(1), eff. September 1, 2021.
(e) Each year, the state board shall deliver to the water development board a report regarding progress made on items listed in the plan. If an update to the report or plan is necessary before the yearly report or before the end of the 10-year cycle, the state board must deliver to the water development board an amended report or plan.
(f) The state board shall consider the timelines for grant applications for the dam structural repair grant program under § 201.0226 when preparing and adopting a plan under this section.