Sec. 23. (a) Except as provided in subsection (b), an entity shall consider statements in the order in which the statements are received by the entity.

     (b) A statement provided by a new applicant who desires to bid on an advertised project must be received not later than forty-five (45) calendar days before the bid opening to receive consideration for that bid opening. A statement provided by a contractor applying for prequalification renewal must be received at least fifteen (15) calendar days before the bid opening date to receive consideration for that bid opening.

As added by P.L.85-1991, SEC.3.

Terms Used In Indiana Code 36-1-9.5-23

  • applicant: means a contractor or the subcontractor who seeks to do business with an entity. See Indiana Code 36-1-9.5-3
  • contractor: means an individual, a partnership, a firm, a limited liability company, a corporation, or other person contracting with or desiring to contract with an entity for performance of prescribed work. See Indiana Code 36-1-9.5-10
  • entity: means the following:

    Indiana Code 36-1-9.5-11