(a) An appeal under this subchapter, Subchapter D, or Subchapter E is de novo and based on the test year presented to the municipality.
(b) The commission shall enter a final order establishing the rates the commission determines the municipality should have set in the ordinance to which the appeal applies.

Terms Used In Texas Utilities Code 33.054

  • Appeal: A request made after a trial, asking another court (usually the court of appeals) to decide whether the trial was conducted properly. To make such a request is "to appeal" or "to take an appeal." One who appeals is called the appellant.
  • Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
  • Year: means 12 consecutive months. See Texas Government Code 311.005

(c) In a proceeding involving the rates of a municipally owned utility, the commission must enter a final order on or before the 185th day after the date the appeal is perfected or the utility files a rate application as prescribed by § 33.104.
(d) In a proceeding in which a rate change is concurrently sought from the commission under the commission’s original jurisdiction, the commission must enter a final order on or before the later of the 120th day after the date the appeal is perfected or the date final action must be taken in the proceeding filed with the commission.
(e) In a proceeding not governed by Subsection (c) or (d), the commission must enter a final order on or before the 185th day after the date the appeal is perfected.
(f) If the commission fails to enter a final order before the expiration of the applicable period prescribed by Subsections (c)-(e), the rates proposed by the utility are considered to be approved by the commission and take effect on the expiration of that period.