1.  To perfect a lien, a lien claimant must record a notice of lien in the office of the county recorder of the county where the property or some part thereof is located in the form provided in subsection 5:

Attorney's Note

Under the Nevada Revised Statutes, punishments for crimes depend on the classification. In the case of this section:
ClassPrisonFine
gross misdemeanorup to 364 daysup to $2,000
For details, see Nev. Rev. Stat. § 193.140

Need help reviewing a real estate contract?
Have it reviewed by a lawyer, get answers to your questions and move forward with confidence.
Connect with a lawyer now

Terms Used In Nevada Revised Statutes 108.226

  • Contract: A legal written agreement that becomes binding when signed.
  • county: includes Carson City. See Nevada Revised Statutes 0.033
  • Lien: A claim against real or personal property in satisfaction of a debt.
  • Oath: A promise to tell the truth.
  • person: means a natural person, any form of business or social organization and any other nongovernmental legal entity including, but not limited to, a corporation, partnership, association, trust or unincorporated organization. See Nevada Revised Statutes 0.039

(a) Within 90 days after the date on which the latest of the following occurs:

(1) The completion of the work of improvement;

(2) The last delivery of material or furnishing of equipment by the lien claimant for the work of improvement; or

(3) The last performance of work by the lien claimant for the work of improvement; or

(b) Within 40 days after the recording of a valid notice of completion, if the notice of completion is recorded and served in the manner required pursuant to NRS 108.228.

2.  The notice of lien must contain:

(a) A statement of the lienable amount after deducting all just credits and offsets.

(b) The name of the owner if known.

(c) The name of the person by whom the lien claimant was employed or to whom the lien claimant furnished the material or equipment.

(d) A brief statement of the terms of payment of the contract.

(e) A description of the property to be charged with the notice of lien sufficient for identification.

3.  The notice of lien must be verified by the oath of the lien claimant or some other person. The notice of lien need not be acknowledged to be recorded.

4.  It is unlawful for a person knowingly to make a false statement in or relating to the recording of a notice of lien pursuant to the provisions of this section. A person who violates this subsection is guilty of a gross misdemeanor and shall be punished by a fine of not less than $5,000 nor more than $10,000.

5.  A notice of lien must be substantially in the following form:

6.  Except as otherwise provided in subsection 7, if a work of improvement involves the construction, alteration or repair of multifamily or single-family residences, including, without limitation, apartment houses, a lien claimant, except laborers, must serve a 15-day notice of intent to lien incorporating substantially the same information required in a notice of lien upon both the owner and the reputed prime contractor before recording a notice of lien. Service of the notice of intent to lien must be by personal delivery or certified mail and will extend the time for recording the notice of lien described in subsection 1 by 15 days. A notice of lien for materials or equipment furnished or to be furnished for work or services performed or to be performed, except labor, for a work of improvement involving the construction, alteration or repair of multifamily or single-family residences may not be perfected or enforced pursuant to NRS 108.221 to 108.246, inclusive, unless the 15-day notice of intent to lien has been given to the owner.

7.  The provisions of subsection 6 do not apply to the construction of any nonresidential construction project.